February 8, 2026 10 min read

The International Federation of Consulting Engineers (FIDIC) publishes the most widely used standard form contracts for international construction projects. Among these, the Red Book — formally titled "Conditions of Contract for Construction for Building and Engineering Works Designed by the Employer" — is the most commonly encountered by Indian contractors working on projects funded by multilateral development banks such as the World Bank, ADB, and AfDB.

At ESB Global Law Advisory, we regularly advise Indian construction companies, EPC contractors, and infrastructure developers on FIDIC contract negotiation, claims management, and dispute resolution. This guide covers the clauses that matter most.

The FIDIC Rainbow: Which Book Applies?

FIDIC publishes several contract forms, each colour-coded for different project delivery methods:

  • Red Book — Construction contracts where the Employer provides the design
  • Yellow Book — Plant and design-build contracts where the Contractor designs
  • Silver Book — EPC/Turnkey projects with maximum risk on the Contractor
  • Green Book — Short-form contract for smaller works
  • Gold Book — Design-Build-Operate (DBO) contracts

The Red Book is predominant in government-funded infrastructure projects across the Middle East, Africa, and Southeast Asia — regions where Indian contractors have a significant presence.

Clause 1: General Provisions and the Role of the Engineer

Unlike Indian construction contracts under the Indian Contract Act, FIDIC contracts introduce the Engineer as a quasi-independent third party who administers the contract, certifies payments, and makes initial determinations on claims. The 2017 edition strengthened the Engineer's obligation to act fairly between the parties under Sub-Clause 3.7.

Indian contractors accustomed to bilateral contracts between Owner and Contractor must understand that the Engineer's determinations are binding unless challenged through the dispute resolution mechanism within the prescribed timeframes.

Clause 8: Time for Completion and Extensions

Time management is critical under FIDIC. Sub-Clause 8.4 entitles the Contractor to an Extension of Time (EOT) for events including:

  • Variations ordered by the Employer or Engineer
  • Exceptionally adverse climatic conditions
  • Unforeseeable physical conditions (Sub-Clause 4.12)
  • Employer-caused delays in providing site access, drawings, or approvals
  • Force Majeure events (Clause 18)

The Contractor must give notice of delay within 28 days of becoming aware of the delaying event. Failure to comply with this notice period can result in loss of the EOT entitlement entirely — a harsh but consistently enforced provision.

Clause 13: Variations and Adjustments

Variations are one of the most frequent sources of disputes in international construction. Under the Red Book, only the Engineer can instruct variations, and the Contractor is generally obligated to comply. However, the Contractor can object if the variation would fundamentally alter the nature of the works.

The 2017 edition introduced a clearer valuation mechanism in Sub-Clause 13.3, requiring the Engineer to agree on rates before the varied work commences where practicable. This is a significant improvement for contractors who previously had to execute varied work without knowing the applicable rate.

Clause 14: Contract Price and Payment

Payment under the Red Book follows a measurement-based system. The Contractor submits monthly Interim Payment Applications, which the Engineer certifies within 28 days. The Employer must pay within 56 days of the Engineer's certification.

Late payment entitles the Contractor to financing charges under Sub-Clause 14.8. If the Employer fails to pay for 42 days beyond the due date, the Contractor can suspend work (Sub-Clause 16.1) — a powerful remedy that Indian contractors should be aware of but use cautiously.

Clause 20: Claims and Dispute Resolution — The Most Critical Clause

Clause 20 is arguably the most important provision in any FIDIC contract. The 2017 edition overhauled the dispute resolution process with a tiered mechanism:

  1. Notice of Claim — Within 28 days of becoming aware of the event (Sub-Clause 20.2.1). This is a strict time bar.
  2. Fully Detailed Claim — Within 84 days of the notice, including full substantiation, supporting documents, and the basis for the claimed amount/time.
  3. Engineer's Determination — The Engineer must respond with a determination under Sub-Clause 3.7.
  4. DAAB Referral — If either party is dissatisfied, the dispute is referred to the Dispute Avoidance/Adjudication Board for a binding decision.
  5. ICC Arbitration — The final tier, with the seat of arbitration typically specified in the Particular Conditions.

Indian contractors must establish robust claims management systems that ensure the 28-day notice period is never missed. In practice, this means project managers need training on FIDIC notice requirements, and legal counsel should review potential claims weekly.

Frequently Asked Questions

The FIDIC Red Book (Conditions of Contract for Construction) is used for building and engineering works designed by the Employer. It is the most widely used international construction contract form, adopted by multilateral development banks including the World Bank, Asian Development Bank, and African Development Bank. The Red Book places design responsibility on the Employer while the Contractor executes the works per the Employer's design.

Clause 20 of the FIDIC Red Book 2017 governs the claims and dispute resolution process. It requires the claiming party to give notice within 28 days of becoming aware of the event, followed by a fully detailed claim within 84 days. If the claim is not resolved, the dispute moves to the Dispute Avoidance/Adjudication Board (DAAB) for a binding decision, with ICC arbitration as the final remedy. Failure to comply with the 28-day notice requirement can result in loss of entitlement.

Indian contractors working on international projects governed by FIDIC contracts must be aware of several key differences from Indian construction contracts: strict time-bar provisions for claims (28-day notice requirement), the role of the Engineer as contract administrator, international arbitration (typically ICC) instead of Indian arbitration, payment terms based on measurement or milestone certification, and the requirement for performance security typically at 10% of contract value. Indian contractors should engage experienced FIDIC legal counsel before signing to understand risk allocation.

Need FIDIC Contract Advisory?

ESB Global Law Advisory provides end-to-end FIDIC contract services — from pre-bid review and negotiation to claims management and ICC arbitration representation.

Schedule a Consultation